Agile: How to deal with bottle neck approvals outside of SCRUM?

Is there an Agile term for when there is a stakeholder that acts as a bottleneck by jumping in only occasionally to trump decisions made collectively by the team? (ie, upper management who never partake in the process, but will occasionally review work and decide they don’t like it)? I’m familiar with Pig and Chickens. Would this simply be a ‘type of chicken’?

Is there any Agile technique to deal with said type of person? Is there a particular role on the Agile team that should be in charge of managing this type of issue?

An example might be that the product owner is happy, IT is happy, UX is happy, various business roles are happy, and sprints are underway, but suddenly someone’s boss’s boss has decided they want everything put into a PPT deck for them to ‘approve’ where we’re at.

1

This is the Product Owner’s job.

The whole point of the product owner is to act as the point of contact between all the stakeholders (including people like someone’s boss’s boss) and the team itself. In theory, the rest of the team should only ever have to deal with the Product Owner. The Product Owner goes and does all the work of talking to various stakeholders, puts together the stories, and then the team just works on them in order of the set priority, and ignores who requested what. (In practice, it never quite works this way, but close enough.)

However, it is also important to remember what a stakeholder is. A stakeholder is the person who writes the checks. The team gets a list of business requirements, and then fulfills them. Sometimes you get stakeholders who either want something stupid, or who change their mind over and over. That is, unfortunately, their prerogative, after all, the whole point of agile is to let stakeholders change their minds often and to catch stupid decisions faster. Ideally, it is mostly the Product Owner that deals with the stress of all that while the team just takes the stories as they come. Really, the whole point of agile is for stakeholders to determine they don’t like something and actually want something different.

Now this is all business requirements. If this boss’s boss is mucking about with technical decisions, then, well, you have my sympathy. There is no real Agile term for this other than “not agile”. In Agile, the team makes technical decisions, not the stakeholders.

TL;DR – If a stakeholder is overturning business decisions, then this is their prerogative, and it is the Product Owner job to deal with that. If the stakeholder is overturning technical decisions, or overturning any decision mid-sprint, then this is something the Product Owner and Scrum Master should be demanding stop.

More examples of interruptions will be helpful to understand the reasoning why your skip manager or another stakeholder requires “stop everything and do this” type of work.

For “put a PPT together to approve“, could this be the lack of transparency up?

Does your team invite all the stakeholders to attend the demos showing the status/progress of sprint’s deliverables?

What’s the outcome of your planning sessions? Is it something that only your team owns? Do you communicate the stories and priorities you’ve agreed on to your top management (Is this information easily accessible/discoverable?)

I do agree with Steven, if the mid-sprint change is driven by a business need or is the result of a micro-management are two different cases.

When business requires changing the direction – that’s the whole reason you do agile then. If that’s the case and you think it happens quite often, consider shortening your iterations or going full-blown Kanban instead?

If that’s a micromanagement issue, protect your team, communicate the ground rules to your management – once the planning is done, no new work can be injected into sprint – it will have to wait until the next sprint. Usually, if the iterations are short – a week long – hardly anyone objects waiting a week max if they have a request. Back it up with data – showing how velocity suffers when sprints are interrupted, explaining how context switching is wasteful, etc.

Trang chủ Giới thiệu Sinh nhật bé trai Sinh nhật bé gái Tổ chức sự kiện Biểu diễn giải trí Dịch vụ khác Trang trí tiệc cưới Tổ chức khai trương Tư vấn dịch vụ Thư viện ảnh Tin tức - sự kiện Liên hệ Chú hề sinh nhật Trang trí YEAR END PARTY công ty Trang trí tất niên cuối năm Trang trí tất niên xu hướng mới nhất Trang trí sinh nhật bé trai Hải Đăng Trang trí sinh nhật bé Khánh Vân Trang trí sinh nhật Bích Ngân Trang trí sinh nhật bé Thanh Trang Thuê ông già Noel phát quà Biểu diễn xiếc khỉ Xiếc quay đĩa Dịch vụ tổ chức sự kiện 5 sao Thông tin về chúng tôi Dịch vụ sinh nhật bé trai Dịch vụ sinh nhật bé gái Sự kiện trọn gói Các tiết mục giải trí Dịch vụ bổ trợ Tiệc cưới sang trọng Dịch vụ khai trương Tư vấn tổ chức sự kiện Hình ảnh sự kiện Cập nhật tin tức Liên hệ ngay Thuê chú hề chuyên nghiệp Tiệc tất niên cho công ty Trang trí tiệc cuối năm Tiệc tất niên độc đáo Sinh nhật bé Hải Đăng Sinh nhật đáng yêu bé Khánh Vân Sinh nhật sang trọng Bích Ngân Tiệc sinh nhật bé Thanh Trang Dịch vụ ông già Noel Xiếc thú vui nhộn Biểu diễn xiếc quay đĩa Dịch vụ tổ chức tiệc uy tín Khám phá dịch vụ của chúng tôi Tiệc sinh nhật cho bé trai Trang trí tiệc cho bé gái Gói sự kiện chuyên nghiệp Chương trình giải trí hấp dẫn Dịch vụ hỗ trợ sự kiện Trang trí tiệc cưới đẹp Khởi đầu thành công với khai trương Chuyên gia tư vấn sự kiện Xem ảnh các sự kiện đẹp Tin mới về sự kiện Kết nối với đội ngũ chuyên gia Chú hề vui nhộn cho tiệc sinh nhật Ý tưởng tiệc cuối năm Tất niên độc đáo Trang trí tiệc hiện đại Tổ chức sinh nhật cho Hải Đăng Sinh nhật độc quyền Khánh Vân Phong cách tiệc Bích Ngân Trang trí tiệc bé Thanh Trang Thuê dịch vụ ông già Noel chuyên nghiệp Xem xiếc khỉ đặc sắc Xiếc quay đĩa thú vị
Trang chủ Giới thiệu Sinh nhật bé trai Sinh nhật bé gái Tổ chức sự kiện Biểu diễn giải trí Dịch vụ khác Trang trí tiệc cưới Tổ chức khai trương Tư vấn dịch vụ Thư viện ảnh Tin tức - sự kiện Liên hệ Chú hề sinh nhật Trang trí YEAR END PARTY công ty Trang trí tất niên cuối năm Trang trí tất niên xu hướng mới nhất Trang trí sinh nhật bé trai Hải Đăng Trang trí sinh nhật bé Khánh Vân Trang trí sinh nhật Bích Ngân Trang trí sinh nhật bé Thanh Trang Thuê ông già Noel phát quà Biểu diễn xiếc khỉ Xiếc quay đĩa

Agile: How to deal with bottle neck approvals outside of SCRUM?

Is there an Agile term for when there is a stakeholder that acts as a bottleneck by jumping in only occasionally to trump decisions made collectively by the team? (ie, upper management who never partake in the process, but will occasionally review work and decide they don’t like it)? I’m familiar with Pig and Chickens. Would this simply be a ‘type of chicken’?

Is there any Agile technique to deal with said type of person? Is there a particular role on the Agile team that should be in charge of managing this type of issue?

An example might be that the product owner is happy, IT is happy, UX is happy, various business roles are happy, and sprints are underway, but suddenly someone’s boss’s boss has decided they want everything put into a PPT deck for them to ‘approve’ where we’re at.

1

This is the Product Owner’s job.

The whole point of the product owner is to act as the point of contact between all the stakeholders (including people like someone’s boss’s boss) and the team itself. In theory, the rest of the team should only ever have to deal with the Product Owner. The Product Owner goes and does all the work of talking to various stakeholders, puts together the stories, and then the team just works on them in order of the set priority, and ignores who requested what. (In practice, it never quite works this way, but close enough.)

However, it is also important to remember what a stakeholder is. A stakeholder is the person who writes the checks. The team gets a list of business requirements, and then fulfills them. Sometimes you get stakeholders who either want something stupid, or who change their mind over and over. That is, unfortunately, their prerogative, after all, the whole point of agile is to let stakeholders change their minds often and to catch stupid decisions faster. Ideally, it is mostly the Product Owner that deals with the stress of all that while the team just takes the stories as they come. Really, the whole point of agile is for stakeholders to determine they don’t like something and actually want something different.

Now this is all business requirements. If this boss’s boss is mucking about with technical decisions, then, well, you have my sympathy. There is no real Agile term for this other than “not agile”. In Agile, the team makes technical decisions, not the stakeholders.

TL;DR – If a stakeholder is overturning business decisions, then this is their prerogative, and it is the Product Owner job to deal with that. If the stakeholder is overturning technical decisions, or overturning any decision mid-sprint, then this is something the Product Owner and Scrum Master should be demanding stop.

More examples of interruptions will be helpful to understand the reasoning why your skip manager or another stakeholder requires “stop everything and do this” type of work.

For “put a PPT together to approve“, could this be the lack of transparency up?

Does your team invite all the stakeholders to attend the demos showing the status/progress of sprint’s deliverables?

What’s the outcome of your planning sessions? Is it something that only your team owns? Do you communicate the stories and priorities you’ve agreed on to your top management (Is this information easily accessible/discoverable?)

I do agree with Steven, if the mid-sprint change is driven by a business need or is the result of a micro-management are two different cases.

When business requires changing the direction – that’s the whole reason you do agile then. If that’s the case and you think it happens quite often, consider shortening your iterations or going full-blown Kanban instead?

If that’s a micromanagement issue, protect your team, communicate the ground rules to your management – once the planning is done, no new work can be injected into sprint – it will have to wait until the next sprint. Usually, if the iterations are short – a week long – hardly anyone objects waiting a week max if they have a request. Back it up with data – showing how velocity suffers when sprints are interrupted, explaining how context switching is wasteful, etc.

Trang chủ Giới thiệu Sinh nhật bé trai Sinh nhật bé gái Tổ chức sự kiện Biểu diễn giải trí Dịch vụ khác Trang trí tiệc cưới Tổ chức khai trương Tư vấn dịch vụ Thư viện ảnh Tin tức - sự kiện Liên hệ Chú hề sinh nhật Trang trí YEAR END PARTY công ty Trang trí tất niên cuối năm Trang trí tất niên xu hướng mới nhất Trang trí sinh nhật bé trai Hải Đăng Trang trí sinh nhật bé Khánh Vân Trang trí sinh nhật Bích Ngân Trang trí sinh nhật bé Thanh Trang Thuê ông già Noel phát quà Biểu diễn xiếc khỉ Xiếc quay đĩa Dịch vụ tổ chức sự kiện 5 sao Thông tin về chúng tôi Dịch vụ sinh nhật bé trai Dịch vụ sinh nhật bé gái Sự kiện trọn gói Các tiết mục giải trí Dịch vụ bổ trợ Tiệc cưới sang trọng Dịch vụ khai trương Tư vấn tổ chức sự kiện Hình ảnh sự kiện Cập nhật tin tức Liên hệ ngay Thuê chú hề chuyên nghiệp Tiệc tất niên cho công ty Trang trí tiệc cuối năm Tiệc tất niên độc đáo Sinh nhật bé Hải Đăng Sinh nhật đáng yêu bé Khánh Vân Sinh nhật sang trọng Bích Ngân Tiệc sinh nhật bé Thanh Trang Dịch vụ ông già Noel Xiếc thú vui nhộn Biểu diễn xiếc quay đĩa Dịch vụ tổ chức tiệc uy tín Khám phá dịch vụ của chúng tôi Tiệc sinh nhật cho bé trai Trang trí tiệc cho bé gái Gói sự kiện chuyên nghiệp Chương trình giải trí hấp dẫn Dịch vụ hỗ trợ sự kiện Trang trí tiệc cưới đẹp Khởi đầu thành công với khai trương Chuyên gia tư vấn sự kiện Xem ảnh các sự kiện đẹp Tin mới về sự kiện Kết nối với đội ngũ chuyên gia Chú hề vui nhộn cho tiệc sinh nhật Ý tưởng tiệc cuối năm Tất niên độc đáo Trang trí tiệc hiện đại Tổ chức sinh nhật cho Hải Đăng Sinh nhật độc quyền Khánh Vân Phong cách tiệc Bích Ngân Trang trí tiệc bé Thanh Trang Thuê dịch vụ ông già Noel chuyên nghiệp Xem xiếc khỉ đặc sắc Xiếc quay đĩa thú vị
Trang chủ Giới thiệu Sinh nhật bé trai Sinh nhật bé gái Tổ chức sự kiện Biểu diễn giải trí Dịch vụ khác Trang trí tiệc cưới Tổ chức khai trương Tư vấn dịch vụ Thư viện ảnh Tin tức - sự kiện Liên hệ Chú hề sinh nhật Trang trí YEAR END PARTY công ty Trang trí tất niên cuối năm Trang trí tất niên xu hướng mới nhất Trang trí sinh nhật bé trai Hải Đăng Trang trí sinh nhật bé Khánh Vân Trang trí sinh nhật Bích Ngân Trang trí sinh nhật bé Thanh Trang Thuê ông già Noel phát quà Biểu diễn xiếc khỉ Xiếc quay đĩa
Thiết kế website Thiết kế website Thiết kế website Cách kháng tài khoản quảng cáo Mua bán Fanpage Facebook Dịch vụ SEO Tổ chức sinh nhật